Design process

Website project dragging on for months? The 7-stage process we use

By RED8 on 28 November 2026
Agenciex template pages laid out side by side, ready to launch

Website projects rarely fail because of bad design. They stall. The brief was vague, the content arrived late, five people gave conflicting feedback, and the launch date quietly moved three times.

A clear process fixes most of this. It is not about paperwork. It is about making each decision at the right time, so nobody redesigns the homepage in week eight. Here is the seven-stage process we follow on our Framer projects, with what to agree before moving on.

In short
  • Agree goals, audience and one measure of success before any design starts.
  • Write the content early and design around real words, not placeholder text.
  • Settle structure and wireframes before colors and fonts.
  • Give feedback in planned rounds, from one owner, with a deadline.
The seven stages

1. Brief: agree what success means.

Write down who the site is for, what they need to do there, what the business needs from it and how you will measure it, for example enquiries per month. Name one person who makes final decisions.

2. Content: write before you design.

Draft the key messages, page copy and calls to action, and gather real photos and proof such as testimonials, client logos and numbers. A design built around real content needs far fewer revisions.

3. Structure: map the pages.

Sketch a simple sitemap and decide what each page is for. This is also the moment to plan CMS collections for repeated content like projects, posts or team members.

4. Wireframes: arrange, don't decorate.

Lay out each key page in grayscale on desktop and phone. Agree the order of sections and the main action on each page before any styling.

5. Visual design: build a small system.

Choose type, colors, spacing and buttons as reusable styles and components, then apply them to the key pages. A system keeps the site consistent as it grows.

6. Build and review: one round at a time.

Build in Framer, share a preview link and collect feedback in two or three planned rounds. Each round has a deadline and ends with one combined list of changes.

7. Check and launch: test like a visitor.

Test every page on real phones, submit every form, check titles, descriptions and redirects, then publish and watch analytics for the first few weeks.

Agenciex Framer template homepage shown on a laptop and a phone
Why content comes before design

The most common delay we see is a beautiful layout waiting for words. When the copy finally arrives it is twice as long, or half as long, or says something the design never planned for, and pages get reworked.

Writing first also forces the hard decisions early: what you actually offer, who it is for and why someone should choose you. Those answers shape the design far more than any mood board.

How to give feedback that helps

Feedback slows projects when it is scattered across emails, chats and calls, or when it describes solutions instead of problems. "Make the logo bigger" is a solution. "I am not sure visitors will notice who we are" is a problem the designer can solve in several ways.

Collect feedback in one place, from one owner who merges the team's views, and agree on a fixed number of rounds before the project starts.

A worked example

Imagine a boutique hotel that wants more direct bookings. The brief sets one goal: double the booking requests that come through the website within six months. The content stage produces room descriptions, a clear rate policy and guest reviews. The sitemap has six pages and a rooms collection. Wireframes put the booking button in the header and after every room, and the visual design uses the hotel's own photography.

Because content and structure were agreed early, the build takes two weeks and needs only two rounds of feedback.

Common mistakes
  • Designing the homepage before anyone agrees what the site is for.
  • Designing with placeholder text and stock photos.
  • Letting new people join late and reopen settled decisions.
  • Unlimited feedback rounds with no deadlines.
  • Treating launch as the end, when the first month of real visitors teaches you the most.
Before you call it ready
  • Every page has one clear main action.
  • All copy is final and proofread.
  • Every page works on a real phone.
  • Forms send to the right inbox.
  • Titles, descriptions, social images and redirects are set.
  • Analytics records visits and form submissions.
Questions people ask

How long should a website project take?

A focused marketing site of five to ten pages usually takes four to eight weeks. Most of the difference comes from how quickly content and feedback arrive.

Can a template shorten the process?

Yes. A good template covers much of the structure, wireframe and visual design work, so you can spend more time on content and checks.

Who should make the final decisions?

Someone senior enough to settle disagreements and available enough to reply within a day or two.

Need a hand?

At RED8 we design and build Framer websites and publish our own Framer templates. If you want a website project that runs to plan, see our website services or share your brief.